Use the right measure for the decision
Use the measure that matches the decision. Reorder point tells you when available stock is low enough to place a replenishment order. Safety stock is the buffer protecting against demand or delivery variation; it is not a sales target. Days of cover shows how long current inventory may last. Cash tied up shows how much money is committed to unsold goods.
These measures answer different questions, so do not substitute one for another. The inventory reorder calculator can help check the arithmetic. ORVX reports inventory position, dead stock and remaining stock value alongside product profitability.
| Measure | Basic calculation | Act when |
|---|---|---|
| Reorder point | Demand during lead time + safety stock | Available stock reaches this level; it signals a replenishment decision. |
| Safety stock | Extra units held above expected demand | Review when delivery reliability or demand variability makes stockouts costly. |
| Days of cover | Units on hand ÷ average daily units sold | Compare against the time until the next usable supply arrives. |
| Cash tied up | Unsold units × unit cost | Act when inventory absorbs cash needed for advertising, fees or operating expenses. |
Forecast from your own sales history
Start with your own shipped-order history at SKU level. Count units shipped by week, remove cancelled orders, and record returns separately. A simple baseline is the average of recent comparable weeks: if a gadget shipped 12, 15, 9 and 14 units, the forecast is 12.5 units per week. Use a recent weighted average when the product is clearly accelerating or slowing, but label one-off promotions and influencer spikes rather than letting them set the normal rate.
Adjust the baseline for what the order history missed. A week with two in-stock days and 10 shipped units is not comparable with a full week; record the stockout and use the product’s shipped-per-in-stock-day rate to estimate the lost selling opportunity. Do not treat returned units as retained demand. Track gross units shipped, units returned and units still sellable, since a resellable return can come back into available stock. Review the forecast against actuals each week and change it when the error is persistent.
For a new gadget, use a closely related SKU in your own store only as a temporary starting point, then replace it quickly with its own data. For inconsistent sales, show a base case and a lower case rather than hiding volatility in one average. ORVX can forecast coming-period revenue from your completed months by arithmetic and publish the method’s backtested error; use that as a revenue check, not a unit-demand guarantee.
Worked example with sample numbers
This example is illustrative. It uses sample numbers for a dropshipping gadgets store selling in Singapore. They are made up to show the method, they are not a benchmark, and your own figures will differ.
Formula: Reorder point = daily units x (lead time + safety days).
| Input | Value |
|---|---|
| Units sold per day | 11 |
| Supplier lead time in days | 30 |
| Safety cover in days | 10 |
| Reorder at | 11 x (30 + 10) = 440 units |
| Cash tied up at cost | S$9869.02 |
Run the same sum with your own numbers in the free calculator, or browse guides for sellers in Singapore and more dropshipping gadgets guides.
General information only: tax, duty and import rules change and depend on your situation, so check with an accountant or the official source before acting.
Eligible Shopify stores can see these numbers for their own store through the Founding 10,000 offer.
Set lead times and safety stock
Set one replenishment lead time for each supplier and shipping route, using business days consistently. Add supplier processing time, freight transit, customs handling and local delivery to the customer or fulfilment point. Freight time alone understates the wait: a parcel can be ready to ship while still waiting for consolidation, clearance or handoff to a Singapore last-mile carrier. Record the elapsed time for completed replenishments, then use a cautious value when those stages vary.
Calculate demand during lead time as average daily unit demand multiplied by total lead-time days. Then calculate the reorder point as: demand during lead time + safety stock. The reorder point is the action threshold for placing an order; safety stock is the separate buffer protecting against demand spikes or delayed processing, freight, customs or delivery.
Choose safety stock from the uncertainty you can observe: use a larger buffer when demand or supplier timing is volatile, and a smaller one when both are stable. Review it when route performance changes. Apply the formula to inventory position, including confirmed inbound units, rather than on-hand units alone. Use the inventory reorder calculator to check the calculation before setting a SKU’s trigger.
Read the worked cash example
Read the worked cash example from left to right. Units are the quantity in the proposed reorder, while reorder quantity is the amount you would ask the supplier to ship. Supplier cost is the product purchase price per unit. Inbound costs cover expenses required to get that batch to Singapore, such as freight or handling; check that they use the same currency and allocation basis as the supplier cost.
Cash committed is the immediate funding requirement for the batch: supplier cost multiplied by units, plus the inbound costs shown in the table. Selling price is different: it indicates potential sales value per unit, not money you have invested or profit you have earned. Compare alternatives by asking how much cash each reorder ties up, then whether its selling price leaves enough room after product, inbound, advertising, payment and return costs. For a second check, use the inventory reorder calculator with the same assumptions.
| Table figure | What it represents | Use it to compare |
|---|---|---|
| Units | Quantity in the proposed batch | How many items arrive |
| Reorder quantity | Amount requested from the supplier | Size of the replenishment |
| Supplier cost | Purchase cost per unit | Product cost |
| Inbound costs | Costs of bringing the batch in | Delivered batch cost |
| Selling price | Customer-facing price per unit | Potential sales value |
| Cash committed | Supplier spend plus inbound costs | Funding required now |
Measure the cost of holding stock
Track committed cash separately from accounting profit. Committed cash is money tied up before a gadget sells: supplier purchase cost, international shipping, Singapore delivery or handling, storage, and any payment due before the customer pays. Include payment timing: a supplier paid upfront creates a cash requirement even if the stock will not be sold for weeks. The current GST rate in Singapore is 9%, according to the Inland Revenue Authority of Singapore; record GST according to your business’s tax treatment rather than assuming it is recoverable.
Accounting profit answers a different question. Product cost is usually recognised when the unit is sold, while storage, payment fees and other operating costs may be recorded separately. Add the risks that cash planning can miss: markdowns, damaged units, refunds and return shipping, and gadgets that remain unsold. For illustration only, $1,000 of stock purchased today is a $1,000 cash commitment, not $1,000 of current profit or loss; a $300 markdown later reduces the eventual margin. ORVX reports delivered-order revenue, product cost, profitability, return value, dead stock and remaining stock value, so compare the inventory position with realised product economics before committing more cash.
Plan around Singapore’s seasonal peaks
Treat a peak as a change to the forecast window, not proof that normal demand has permanently risen. Build a temporary scenario for a campaign, gifting period, school break or term start, and payday cluster. For illustration only, if normal weekly sales are 40 phone stands and a campaign adds 25 units for two weeks, plan for 65 during those weeks, then return to 40 unless shipped-order data shows a sustained lift.
Change timing as well as units. Weather-sensitive demand may shift toward waterproof accessories during wetter periods, while school schedules can move demand for study or travel gadgets. Confirm supplier closures and carrier capacity before the event. If replenishment normally takes 12 business days and a closure adds 5, use 17 business days for that event’s lead-time assumption and keep the extra buffer tied to it.
Do not permanently raise reorder levels for a short spike. Use an event plan with start and end dates, a separate uplift assumption and a post-event review. Compare delivered units, cancellations, returns and remaining stock with the plan; revise the normal baseline only when higher demand repeats outside the event.
A useful inventory plan connects three decisions: how much demand your own data supports, how long replenishment takes to reach Singapore, and how much cash can remain committed without putting the business under pressure. Review the forecast, reorder point and holding cost together before placing each purchase order.
Sources
- Current GST rates (Inland Revenue Authority of Singapore, checked 26 October 2026).